ACCA考试回顾,《F2管理会计》讲义辅导(10)

来源: 高顿网校 2015-03-20
  3.3 Analysis of costs into fixed and variable elements:
  High-low method
  Step 1 – select the highest and lowest activity levels, and their associated costs
  Step 2 – find the variable cost per unit
  Step 3 – find the fixed cost by substitution, using either the high or low activity level.
  Example 1:
  Using high-low method to calculate the fixed and variable elements of the following costs:
  Month Units produced Costs ($)
  July 340 2,260
  August 300 2,160
  September 380 2,320
  October 420 2,400
  November 400 2,300
  December 360 2,266
  Solution:
  Step 1- Select the highest and lowest activity levels, and their associated costs
  Month Units produced Cost ($)
  Highest activity level: October 420 2,400
  Lowest activity level: August 300 2,160
  Step 2 – find the variable cost per unit
  Total cost at high activity level – total cost at low activity level
  Variable cost per unit = total units at high activity level – total units at low activity level
  = 2400 – 2160 = $2/unit
  420 – 300
  Step 3 – find the fixed cost by substitution, using either the high or low activity level.
  Fixed cost = (total cost at high activity level) – (total cost at high activity level x variable cost per unit)
  = $2,400 - $2 /unit x 420 units = $1,560
  High- low method with stepped fixed cost
  Sometimes fixed costs are only fixed within certain levels of activity and increase in steps as activity increases:
  · The high low method can still be used to estimate fixed and variable costs
  · Adjustments need to be made for the fixed costs based on the activity level under consideration.
  Example 2:
  An organization has the following total costs at three activity levels:
  Activity levels (units) 12,750 15,100
  Total cost $73,950 $83,585
  Variable cost per unit is constant within this activity range and there is a step up of $4,700 in the total fixed costs when the activity level exceeds 14,000 units.
  Required: what is the total cost at an activity level of 14,500 units?
  Solution:
  Unit produced Cost ($)
  Highest activity level: 15100 73950
  Lowest activity level: 12750 83585- 4700
  Variable cost = (83585-4700 – 73950)/ (15100- 12750) = $2.1/unit
  Fixed cost exceeds 14500 units = 83585 - $2.1 x 15100 = $51,875
  Total cost for 14500 units = $51,875 + $2.1 x 14500 units = $82,325
  High –low method with changes in the variable cost per unit
  Sometimes there may be changes in the variable cost per unit, and the high low method can still be used to determine the fixed and variable elements of semi-variable costs. The variable cost per unit may change because:
  · Prices may be forecast to increase in future periods
  · Bulk discounts may be available for purchasing resources in large quantities. Example 3:
  The following information relates to the manufacture of product LL in 2009.
  Output (units) Total cost ($)
  200 7,000
  300 8,000
  400 8,600
  For output volumes above 350 units, the variable cost per unit falls by 10%. (Note: this fall applies to all units – not just the excess above 350.)
  Required: estimate the cost of producing 450 units of Product LL in 2010.
  Solution:
  If output volumes below 350 units: variable cost = (8000 – 7000)/ (300-200)
  = $10/unit
  If output volume above 350 units: variable cost = $10 x 90% = $9
  Fixed cost = $8,600 – 400 x $9 = $5,000
  Total cost for 450 units = $5,000 + 450 units x $9 = $9,050
  Example 4:
  1. Which of the following best describe a controllable cost?
  A. A cost which arises from a decision already taken, which cannot, in the short run, be changed.
  B. A cost for which the behavior pattern can be easily analyzed to facilitate valid budgetary control comparisons.
  C. A cost which can be influenced by its budget holder.
  D. A specific cost of an activity or business which would be avoided it the activity or business did not exist.
  Solution: C
  Controllable costs are items of expenditure which can be directly influenced by a given manager within a given time span.
  Example 5:
  A manufacturing firm is very busy and overtime is being worked.
  How would the amount of overtime premium contained in direct wages normally be classified?
  A. Part of prime cost
  B. Factory overheads
  C. Direct labor costs
  D. Administrative overheads
  Solution: B
  Overtime premium is always classified as factory overhead unless it is:
  Worked at the specific request of a customer to get his order completed
  Worked regularly by a production department in the normal course of operations, in which case it is usually incorporated into the direct labor hourly rate.
  Example 6:
  A company employs four supervisors to oversee the factory production of all its products. How would the salaries paid to these supervisors be classified?
  A. As a direct labour cost
  B. As a direct production expense
  C. As a production overhead
  D. As an administration overhead
  Solution:
  The supervisors are engaged in the production activity, therefore option D can be eliminated. They supervise the production of all products, therefore their salaries are indirect costs because they cannot be specifically identified with a cost unit. This eliminates options A and B. The salaries are indirect production overhead costs, therefore option C is correct.
没有目标就没有方向,每一个学习阶段都应该给自己树立一个目标。 高顿网校为广大学员提供2015年ACCA考试网络课程,让您向自己的目标不断前进,2015年考试顺利通过!祝您梦想成真!免费听课》
ACCA网络课程课程专业名称讲师试听
85%的人正在学习该课程ACCA 全维度网课体验课程
实景课堂与独立录制
覆盖所有知识点,根据学习计划推进学习进度
高顿名师
70%的人正在学习该课程ACCA网课全科卡(8.2折)
为零基础刚开始学习ACCA的学员特别定制
高顿名师

acca备考 热门问题解答
acca考试怎么搭配科目?

建议优先选择相关联的科目进行搭配报考,这样可以提高备考效率,减轻备考压力,1、F1-F4:为随时机考科目,难度较低,这里可以自行随意选择考试顺序。2、F5-F9:如果你的工作的和财务会计或者审计有关、或者你比较擅长财务和审计的话,推荐先考F7和F8。你可以选择一起考ACCA考试科目F7和F8或者先考F7(8)再考F8(7),这就要取决你一次想考几门。3、P阶段:选修科目中,建议企业首选AFM!第二部分科目进行选择,如果AA和SBR掌握学生更好,可以通过选择AAA,如果SBL掌握的好,可以自己选择APM。

acca一共几门几年考完?

acca一共有15门考试科目,其中有必修科目和选修科目,考生需要考完13门科目才能拿下证书。

acca一年考几次?

acca一年有4次考试,分别是3月、6月、9月和12月,分季机考科目是采取的这类四个考季的模式,而随时机考则是没有这方面的时间规定限制,可以随报随考。

acca的含金量如何?

ACCA证书的含金量是比较高的,从就业、能力提升、全球认可等角度来说,都是比较有优势的证书,其含金量主要表现在以下几个方面:1、国际化,认可度高;2、岗位多,就业前景好;3、缺口大,人才激励。

在线提问
严选名师 全流程服务

Sdanvi

高顿ACCA全学科负责人

教学特色
自创“少女三大法则”和“二阶学习法”
教学资历
两年内高分通过ACCA考试,ACCA业界学霸型讲师
客户评价
帮助学生快速理解ACCA的知识点,是ACCA学习不可错过的宝藏博主
sdanvi
  • 老师好,考出ACCA的难度相当于考进什么大学?
  • 老师好,ACCA考试怎样备考(越详细越好)?
  • 老师好,38岁才开始考ACCA会不会太迟?
  • 老师好,ACCA通过率是多少?
  • 老师好,有了ACCA证后好找工作吗?
999+人提问

Perry

高顿acca明星讲师

学历背景
复旦-麻省理工国际工商管理硕士
教学资历
曾就职于四大、世界500强
客户评价
ACCA业界学霸型讲师
Perry
  • 老师好,acca如果不去考会怎么样?
  • 老师好,acca难度有多大?
  • 老师好,acca一年可以考多少门?
  • 老师好,acca考试科目几年考完?
  • 老师好,acca工资一般是多少钱?
999+人提问

Dora

高顿acca明星讲师

学历背景
英国布里斯托优秀硕士生
教学资历
多年普华永道金融组审计师经验
客户评价
知性又美丽,温柔大姐姐
Dora
  • 老师好,acca持证工资待遇如何?
  • 老师好,35岁考acca有意义吗?
  • 老师好,考过acca能干嘛?
  • 老师好,考完acca可以做什么工作?
  • 老师好,acca年薪一般多少?
999+人提问

高顿教育 > ACCA > 基础阶段F系列