ACCA考试回顾,《F2管理会计》讲义辅导(10)
来源:
高顿网校
2015-03-20
3.3 Analysis of costs into fixed and variable elements:
High-low method
Step 1 – select the highest and lowest activity levels, and their associated costs
Step 2 – find the variable cost per unit
Step 3 – find the fixed cost by substitution, using either the high or low activity level.
Example 1:
Using high-low method to calculate the fixed and variable elements of the following costs:
Month Units produced Costs ($)
July 340 2,260
August 300 2,160
September 380 2,320
October 420 2,400
November 400 2,300
December 360 2,266
Solution:
Step 1- Select the highest and lowest activity levels, and their associated costs
Month Units produced Cost ($)
Highest activity level: October 420 2,400
Lowest activity level: August 300 2,160
Step 2 – find the variable cost per unit
Total cost at high activity level – total cost at low activity level
Variable cost per unit = total units at high activity level – total units at low activity level
= 2400 – 2160 = $2/unit
420 – 300
Step 3 – find the fixed cost by substitution, using either the high or low activity level.
Fixed cost = (total cost at high activity level) – (total cost at high activity level x variable cost per unit)
= $2,400 - $2 /unit x 420 units = $1,560
High- low method with stepped fixed cost
Sometimes fixed costs are only fixed within certain levels of activity and increase in steps as activity increases:
· The high low method can still be used to estimate fixed and variable costs
· Adjustments need to be made for the fixed costs based on the activity level under consideration.
Example 2:
An organization has the following total costs at three activity levels:
Activity levels (units) 12,750 15,100
Total cost $73,950 $83,585
Variable cost per unit is constant within this activity range and there is a step up of $4,700 in the total fixed costs when the activity level exceeds 14,000 units.
Required: what is the total cost at an activity level of 14,500 units?
Solution:
Unit produced Cost ($)
Highest activity level: 15100 73950
Lowest activity level: 12750 83585- 4700
Variable cost = (83585-4700 – 73950)/ (15100- 12750) = $2.1/unit
Fixed cost exceeds 14500 units = 83585 - $2.1 x 15100 = $51,875
Total cost for 14500 units = $51,875 + $2.1 x 14500 units = $82,325
High –low method with changes in the variable cost per unit
Sometimes there may be changes in the variable cost per unit, and the high low method can still be used to determine the fixed and variable elements of semi-variable costs. The variable cost per unit may change because:
· Prices may be forecast to increase in future periods
· Bulk discounts may be available for purchasing resources in large quantities. Example 3:
The following information relates to the manufacture of product LL in 2009.
Output (units) Total cost ($)
200 7,000
300 8,000
400 8,600
For output volumes above 350 units, the variable cost per unit falls by 10%. (Note: this fall applies to all units – not just the excess above 350.)
Required: estimate the cost of producing 450 units of Product LL in 2010.
Solution:
If output volumes below 350 units: variable cost = (8000 – 7000)/ (300-200)
= $10/unit
If output volume above 350 units: variable cost = $10 x 90% = $9
Fixed cost = $8,600 – 400 x $9 = $5,000
Total cost for 450 units = $5,000 + 450 units x $9 = $9,050
Example 4:
1. Which of the following best describe a controllable cost?
A. A cost which arises from a decision already taken, which cannot, in the short run, be changed.
B. A cost for which the behavior pattern can be easily analyzed to facilitate valid budgetary control comparisons.
C. A cost which can be influenced by its budget holder.
D. A specific cost of an activity or business which would be avoided it the activity or business did not exist.
Solution: C
Controllable costs are items of expenditure which can be directly influenced by a given manager within a given time span.
Example 5:
A manufacturing firm is very busy and overtime is being worked.
How would the amount of overtime premium contained in direct wages normally be classified?
A. Part of prime cost
B. Factory overheads
C. Direct labor costs
D. Administrative overheads
Solution: B
Overtime premium is always classified as factory overhead unless it is:
Worked at the specific request of a customer to get his order completed
Worked regularly by a production department in the normal course of operations, in which case it is usually incorporated into the direct labor hourly rate.
Example 6:
A company employs four supervisors to oversee the factory production of all its products. How would the salaries paid to these supervisors be classified?
A. As a direct labour cost
B. As a direct production expense
C. As a production overhead
D. As an administration overhead
Solution:
The supervisors are engaged in the production activity, therefore option D can be eliminated. They supervise the production of all products, therefore their salaries are indirect costs because they cannot be specifically identified with a cost unit. This eliminates options A and B. The salaries are indirect production overhead costs, therefore option C is correct.
没有目标就没有方向,每一个学习阶段都应该给自己树立一个目标。 高顿网校为广大学员提供2015年ACCA考试网络课程,让您向自己的目标不断前进,2015年考试顺利通过!祝您梦想成真!免费听课》
| ACCA网络课程 | 课程专业名称 | 讲师 | 试听 |
85%的人正在学习该课程 | ACCA 全维度网课体验课程 实景课堂与独立录制 覆盖所有知识点,根据学习计划推进学习进度 | 高顿名师 | ![]() |
70%的人正在学习该课程 | ACCA网课全科卡(8.2折) 为零基础刚开始学习ACCA的学员特别定制 | 高顿名师 | ![]() |
精彩推荐:
版权声明:本条内容自发布之日起,有效期为一个月。凡本网站注明“来源高顿教育”或“来源高顿网校”或“来源高顿”的所有作品,均为本网站合法拥有版权的作品,未经本网站授权,任何媒体、网站、个人不得转载、链接、转帖或以其他方式使用。
经本网站合法授权的,应在授权范围内使用,且使用时必须注明“来源高顿教育”或“来源高顿网校”或“来源高顿”,并不得对作品中出现的“高顿”字样进行删减、替换等。违反上述声明者,本网站将依法追究其法律责任。
本网站的部分资料转载自互联网,均尽力标明作者和出处。本网站转载的目的在于传递更多信息,并不意味着赞同其观点或证实其描述,本网站不对其真实性负责。
如您认为本网站刊载作品涉及版权等问题,请与本网站联系(邮箱fawu@gaodun.com,电话:021-31587497),本网站核实确认后会尽快予以处理。
点一下领资料
【整理版】ACCA各科目历年真题
真题高频考点,刷题全靠这份资料
下载合集
acca全科学习思维导图
梳理核心考点,一图看懂全部章节
下载合集
2023年acca考纲解析
覆盖科目重难点,备考按照计划走
下载合集
acca备考 热门问题解答
- acca考试怎么搭配科目?
-
建议优先选择相关联的科目进行搭配报考,这样可以提高备考效率,减轻备考压力,1、F1-F4:为随时机考科目,难度较低,这里可以自行随意选择考试顺序。2、F5-F9:如果你的工作的和财务会计或者审计有关、或者你比较擅长财务和审计的话,推荐先考F7和F8。你可以选择一起考ACCA考试科目F7和F8或者先考F7(8)再考F8(7),这就要取决你一次想考几门。3、P阶段:选修科目中,建议企业首选AFM!第二部分科目进行选择,如果AA和SBR掌握学生更好,可以通过选择AAA,如果SBL掌握的好,可以自己选择APM。
- acca一共几门几年考完?
-
acca一共有15门考试科目,其中有必修科目和选修科目,考生需要考完13门科目才能拿下证书。
- acca一年考几次?
-
acca一年有4次考试,分别是3月、6月、9月和12月,分季机考科目是采取的这类四个考季的模式,而随时机考则是没有这方面的时间规定限制,可以随报随考。
- acca的含金量如何?
-
ACCA证书的含金量是比较高的,从就业、能力提升、全球认可等角度来说,都是比较有优势的证书,其含金量主要表现在以下几个方面:1、国际化,认可度高;2、岗位多,就业前景好;3、缺口大,人才激励。
严选名师 全流程服务
其他人还搜了
热门推荐
-
acca《TX税务》2023-2024考纲变动高达10%,考生请注意! 2023-04-25
-
accaf阶段包括哪几门?这些重点你要注意! 2023-03-30
-
accaF阶段科目考完需要多久?难度大吗? 2023-03-28
-
accaF阶段科目详细信息介绍,这篇介绍全了! 2023-03-23
-
acca《AA审计与认证业务》详细介绍,一文完全了解! 2023-03-17
-
accaF阶段科目介绍,全科难度排序来了! 2023-03-15
-
accaF阶段学多久?学姐经验分享! 2023-03-10
-
accaF阶段科目先考哪个好?报考要注意什么? 2023-02-15
-
accaF8怎么学?备考经验总结! 2023-01-18
-
ACCA考试F阶段考试科目 2022-11-01
-
ACCAf1考试有原题多不多?如何查看考试成绩? 2022-10-19
-
ACCAf阶段的科目内容分别是什么?考试形式是什么? 2022-10-11
-
ACCAf阶段考试科目有哪些?学科内容都是什么? 2022-10-11
-
在上海读ACCA专业的就业前景如何?报名条件是什么? 2022-10-09
-
在上海读ACCA专业的就业前景如何?报名条件是什么? 2022-10-09
-
在上海读ACCA专业的就业前景如何?报名条件是什么? 2022-10-09
-
2023年ACCA考试报名条件是什么?考试报名流程是什么? 2022-09-26
-
2023年3月份考试ACCAf阶段的考试内容是什么?附答题技巧 2022-09-26
-
ACCAf1考试时间是怎么安排的?看完这篇你就知道了 2022-09-13
-
特许公认会计师基础阶段的考试内容是什么?考察什么内容? 2022-09-08
-
ACCA考试FM该怎么学?这份攻略请收好! 2022-09-08
-
ACCA专业的就业前景如何?报名条件是什么? 2022-08-26
-
ACCAf5到f9搭配如何搭配更好?附备考建议! 2022-08-26
-
ACCA要通过多少门才有用?如何申请会员证书? 2022-08-18
-
ACCAf1考试有原题多吗?如何查看考试分数? 2022-08-17
-
12月ACCA报考费用多少钱?报名截止日期什么时候? 2022-08-15
-
ACCA知识体系是什么?附备考攻略! 2022-08-15
-
9月ACCA前四科考试时间是什么时候?附考试攻略! 2022-08-15
-
9月ACCA的F2考试时间是什么时候?什么时候出成绩? 2022-08-12
-
ACCA考下来薪资有多少?考了ACCA有什么好处? 2022-08-08
更多服务






