问题:In 20X5, costs were $1,077,000. In 20X6, activity was up 15% and costs were $1,200,000. Activity is expected to increase by 25% over the 20X6 levels in 20X7.
  What is the expected total level of costs in 20X7?
  $________
  答案:The correct answer is: $1,435,750.
  A 15% activity increase in 20X6 increased costs by $123,000 ($1,200k - $1,077k).
  As fixed costs do not change with output, any change in costs must have been the result of a change in variable costs.
  If 100% of the variable costs in 20X5 were $820,000 (123,000 divided by 15%), fixed costs must have been $257,000 ($1,077,000 - $820,000).
  Variable costs in 20X6 were therefore, $943,000 (820,000 x 1 + 15%).
  A 25% increase in 20X6 variable costs of $943,000 to $1,178,750 gives a total cost of $1,435,750 ($257,000 + $1,178,750).
  高顿网校温馨提醒
  各位考生,2015年ACCA备考已经开始,为了方便各位学员能更加系统地掌握考试大纲的重点知识,帮助大家充分备考,体验实战,高顿网校开通了全免费的ACCA题库(包括精题真题和全真模考系统),题库里附有详细的答案解析,学员可以通过多种题型加强练习。戳这里进入ACCA免费题库>>>
 
ACCA网络课程课程专业名称讲师试听
85%的人正在学习该课程ACCA 全维度网课体验课程
实景课堂与独立录制
覆盖所有知识点,根据学习计划推进学习进度
高顿名师
70%的人正在学习该课程ACCA网课全科卡(8.2折)
为零基础刚开始学习ACCA的学员特别定制
高顿名师

展开全文