Question:----- risks are risks whose only possible outcome are harmful.
A. Speculative risks
B. Operational risks
C. Pure risks
D. Fundamental risks
E. Particular risks
The correct answer is: Pure risks.
解析:Fundamental risks are any risks that affect society in general and can't be controlled by any individual.
Particular risks are risks over which individuals have some measure of control.
Speculative risks are risks from which either good or harm may result.
Operational risks are risks that arise from day-to-day operations.
版权声明:本条内容自发布之日起,有效期为一个月。凡本网站注明“来源高顿教育”或“来源高顿网校”或“来源高顿”的所有作品,均为本网站合法拥有版权的作品,未经本网站授权,任何媒体、网站、个人不得转载、链接、转帖或以其他方式使用。 经本网站合法授权的,应在授权范围内使用,且使用时必须注明“来源高顿教育”或“来源高顿网校”或“来源高顿”,并不得对作品中出现的“高顿”字样进行删减、替换等。违反上述声明者,本网站将依法追究其法律责任。 本网站的部分资料转载自互联网,均尽力标明作者和出处。本网站转载的目的在于传递更多信息,并不意味着赞同其观点或证实其描述,本网站不对其真实性负责。 如您认为本网站刊载作品涉及版权等问题,请与本网站联系(邮箱fawu@gaodun.com,电话:021-31587497),本网站核实确认后会尽快予以处理。
-
ACCA P6《高级税务》讲义详情 高顿教育 2015-09-17 13:14:09
-
ACCA P5《高级业绩管理》讲义辅导 高顿教育 2015-09-17 13:11:11
-
ACCA考试P4《高级财务管理》讲义辅导 高顿教育 2015-09-17 11:54:16
-
ACCA考试P3《商业分析》讲义辅导 高顿教育 2015-09-17 11:50:47
-
ACCA P2《公司报告》基础讲义 高顿教育 2015-09-17 11:48:27
热门评论
写评论
热门推荐