The efficiency variance for either labor or materials can be divided into
A. Yield variance and mix variance.
B. Spending variance and yield variance.
C. Yield variance and price variance.
D. Volume variance and mix variance.
A. The total material quantity (efficiency) and labor efficiency variances can be broken down into two subvariances: the mix and the yield variances. The mix variance is the part of the quantity variance that results because the mix of material actually used was different from the mix that was supposed to have been used. (For example, including more corn and less wheat in the cereal than the standard called for). The yield variance results from the difference between the total quantity of the inputs that were actually used to produce the actual output and the total standard quantity that should have been used to produce the actual output.
B. The total material quantity (efficiency) and labor efficiency variances can be broken down into the two subvariances, but the spending variance is not one of them.
C. The total material quantity (efficiency) and labor efficiency variances can be broken down into the two subvariances, but the price variance is not one of them.
D. The total material quantity (efficiency) and labor efficiency variances can be broken down into the two subvariances, but the volume variance is not one of them.
高顿网校温馨提醒
各位考生,2016年CMA备考已经开始,为了方便各位学员能更加系统地掌握考试大纲的重点知识,帮助大家充分备考,体验实战,高顿网校开通了
CMA题库(包括精题真题和全真模考系统),题库里附有详细的答案解析,学员可以通过多种题型加强练习。
点击进入CMA免费题库>>>微信扫一扫,关注CMA*7资讯,满满的干货喂饱你!CMA微信公众号:chinacmaCMA分享与交流QQ群:247263654
精彩推荐: