Question:Which of the following are risk management policies and which are risk management techniques?
Deciding not to invest in politically unstable countries
Using a forward contract to hedge a major receipt from a customer
Employing local managers to manage overseas operations to reduce the risk of cultural misunderstandings
Assessing the creditworthiness of new overseas customers before extending credit
A. I and II are policies, III and IV are techniques
B. I and IV are policies, II and III are techniques
C. II and III are policies, I and IV are techniques
D. I and III are policies, II and IV are techniques
The correct answer is:I and III are policies, II and IV are techniques.
解析:The difference between the two is that policies relate to high-level, strategic decisions, whereas techniques are specific to particular risks. Strategic decisions include investment decisions and management decisions so I and III are policies. A forward contract hedges a specific receipt however, so it is a technique. The credit check is done for each customer, so that is also a technique.
高顿网校温馨提醒
各位考生,2016年ACCA备考已经开始,为了方便各位学员能更加系统地掌握考试大纲的重点知识,帮助大家充分备考,体验实战,高顿网校开通了全免费的
ACCA题库(包括精题真题和全真模考系统),题库里附有详细的答案解析,学员可以通过多种题型加强练习。
戳这里进入ACCA免费题库>>>微信扫一扫,关注ACCA*7资讯,满满的干货喂饱你!ACCA微信公众号:gaodunacca
ACCA分享与交流QQ群:227573128