Question:When explaining the skills required for effective project management, Mo's manager would have included which three from the following list?
A. Ability to do every team member's job.
B. Evaluating progress towards objectives.
C. Supressing problems arising from changes.
D. Negotiating resolutions to conflict.
E. Selecting the right people.
The correct answers are:Negotiating resolutions to conflict; Selecting the right people; Evaluating progress towards objectives.
解析:To be effective as a project manager Mo needs to be able to select the right people to work on the project. He would also need to negotiate resolutions to conflict and evaluate progress towards objectives. It is not necessary to have the skills of each team member and the project manager needs to be able to heal wounds inflicted by change rather than supress the problems.
高顿网校温馨提醒
各位考生,2016年ACCA备考已经开始,为了方便各位学员能更加系统地掌握考试大纲的重点知识,帮助大家充分备考,体验实战,高顿网校开通了全免费的ACCA题库(包括精题真题和全真模考系统),题库里附有详细的答案解析,学员可以通过多种题型加强练习。戳这里进入ACCA免费题库>>>
精彩推荐:
展开全文
版权声明:本条内容自发布之日起,有效期为一个月。凡本网站注明“来源高顿教育”或“来源高顿网校”或“来源高顿”的所有作品,均为本网站合法拥有版权的作品,未经本网站授权,任何媒体、网站、个人不得转载、链接、转帖或以其他方式使用。 经本网站合法授权的,应在授权范围内使用,且使用时必须注明“来源高顿教育”或“来源高顿网校”或“来源高顿”,并不得对作品中出现的“高顿”字样进行删减、替换等。违反上述声明者,本网站将依法追究其法律责任。 本网站的部分资料转载自互联网,均尽力标明作者和出处。本网站转载的目的在于传递更多信息,并不意味着赞同其观点或证实其描述,本网站不对其真实性负责。 如您认为本网站刊载作品涉及版权等问题,请与本网站联系(邮箱fawu@gaodun.com,电话:021-31587497),本网站核实确认后会尽快予以处理。
-
【每日一题】ACCA P7试题:Group audits and transnational audits 高顿教育 2021-05-27 09:43:04
-
【每日一题】ACCA F6试题:NIC 高顿教育 2021-05-24 14:05:57
-
ACCA考试每日一练:payments account 高顿教育 2017-01-16 14:13:54
-
ACCA考试F1基础测试题集锦 高顿教育 2017-01-10 13:13:23
-
ACCA考试F2基础精练题:Sources of data 高顿教育 2016-11-14 13:12:00
其他人还搜了
热门推荐
ACCA

证书星级
距离ACCA考试仅剩
天
特许公认会计师公会(The Association of Chartered Certified Accountants)简称ACCA,成立于1904年,是目前世界上专业会计师团体,也是国际学员众多、学员规模发展迅速的专业会计师组织。
加载更多
ACCA学习资料